POTHOLING
TAKE A LOOK AT OUR DETAILED REPORTS
Pre-Construction
Pothole Report
Detailed
Diagrams
SCOPE OF WORK
• Execute contract and provide Certificate of Insurance showing all requisite coverage
• Prepare and submit for approval traffic control plans based upon the pothole locations shown on the attached plans
• Obtain all required permits and licenses
• Call in Underground Service Alerts to all pothole locations
• Surface locate designated utility lines to determine approximate alignments for locations
• Uncover and field verify depth of all existing utility facilities per the final potholing list provided by the city and record all data obtained.
DATA TO INCLUDE:
Pothole Number // Owner // Material
size // depth to top // depth to bottom
• Provide depth to bottom of any encasements that are encountered, trenching if required to complete
• Provide an accurate location of each facility found, which includes pothole number.
• Notify the City when all locations are accurately identified to coordinate field survey at each location
• Prepare a draft pothole report, including summary and results, to submit to the City for review
• Address all comments from the City to finalize Pothole Report and resubmit
• Follow City standards to complete pothole repairs at all locations
• Follow City standards to complete trench repairs at all necessary locations